I believe I'm not being clear...
Imagine the following scenario:
- Requirement of 500un on plant 1500 (material "A");
- Material "A" can be produced on plants 1700OR1800;
- Material "A" has a special procurement 40, where procurement type F (external) and special procurement U (stock transfer) are defined for plant 1500. The plant 1800 is defined as production plant (special procurement 40);
- When MRP run, a planned order is created (plant 1800 is the production plant AND the planning plant). It means that the stock will be transferred from 1800 to 1500 at the end of production.
The question is:
If I want to change the production plant to 1700 (the plant 1800 can't produce at the moment, for any reason), what you need to do to have the same behavior?
Material "A" can be produced on plants 1700OR1800 !!! (by default, the plant 1800 is the production plant).
Thanks,
Willian.