Project stock and MD51 (or MD03) use with nonvaluated materials (ie ERSA)

I am looking for some help on a CBP(consumption based planning project) we are implementing for materials we treat financially as non-valuated in  our
business. MD51 works for valued materials with project stock  for us in CBP, but not for non-valuated. I am wondering if we are missing master data or
configuration or limitation or MD51 ? Our scenario:

- We are using material types ROH and ERSA with material type configuration for valuation tracking disabled.

- We stock these materials in project stock with a WBS that is non-valuated and assigned via naming to a supplier name.

- Materials are currently being planned on a external to our SAP system , so no CBP running yet.

- Purchase Requisitions and planned orders are coded for "Q" account assignment for ordering and received against.

- I have MRP2 view /individual collective set to '1'  for these materials.

 

I don't see MD51 when being run for the WBS element for these materials even considering these for CBP run. It ignores with no planning

occurring.

 

Any thoughts appreciated.