Hello all,
The sales order created is not getting displayed in MD04. I know this can be controlled with the 'No MRP' field in the Requirement Class Config. But as in this case the No MRP's value is equivalent to = Requirements Planned. So is there any other option other than this to control the MD04 thing ?
I changed the item category in sales order which had a new schedule line item category populated, the new value went to 'CP' from 'CS' . Then i checked MD04 the sales order was available there.
But with Schedule line Item category 'CS' the sales order went missing from MD04 screen.
Thanks in advance.
Regards,
Rahul