Hello,
I am trying to solve an interesting problem using CTM FFF class. I was wondering if I have to take the custom route to address this issue.
Scenario: (FG- Finished good, COMP-Component)
FG-1 has COMP-1 . After few weeks the BOM is revised and now FG -1 has COMP -2.
There is still supply on COMP 1.
COMP 1 and 2 both have 10 weeks production horizon.
With standard FFF class (COMP-2 as leading product) the planned order on COMP 2 is generated from left over supply of COMP 1 in week 11 (after the production horizon).
But ideally the if the supply on COMP1 is in current week then the planned order on FG also should be in week 1, not after the production horizon. If i run CTM with setting "Ignore master data setting' it creates a planned order in COMP 2 in week 1 and then uses that supply to plan FG in week 1. But that is correct because COMP 2 has 10 weeks production horizon.
Please let me know if this is a limitation or if there is any setting I am missing or if I have to go with a custom development.
Thanks.
Sai.